2013 Scheduled Roadwork Start  From  To  Estimated Cost 
         
Jaeger Road Jun-2013 Leavitt Rd. Kolbe Rd  $ 5,000,000.00
         
SR 611 (W. 21st St.) May-2013 US 6 (W. Erie Ave.) East Corp Line  $ 2,200,000.00
         
Oberlin Ave. Apr-2013 Meister Rd. W. Erie Ave.  $ 1,000,000.00
         
Gargasz Dr. Apr-2013 1200' N of Narragansett Emerald Dr.  $    135,000.00
         
Livingston Ave. May-2013 W. 18th St. W. 20th St.  $      82,000.00
W. 18th St May-2013 Livingston Ave. Broadway Ave.  $    102,000.00
W. 20th St May-2013 Livingston Ave. Broadway Ave.  $      57,950.00
E. 21st St May-2013 CSX RR Tracks Elyria Ave.  $      85,000.00
E. 31st St May-2013 Grove Ave. Charleston Ave.  $    291,200.00
Colorado Ave. May-2013 E. Erie Ave. Lakeside Ave.  $      77,750.00
Old E. Erie Ave. May-2013 Alabama Ave. E. Erie Ave.  $      22,500.00
Oberlin Ave. May-2013 W. Erie Ave. First St.  $      85,000.00
Vine Ave. May-2013 E. 32nd St. E. 30th St.  $    370,000.00
         
Washington Ave. Bridge Replacement Jul-2013      $    185,000.00
         
Reid Ave. Jun-2013 W. 5th St. W. 22nd St.  $    869,000.00
Washington Ave. Jun-2013 W. 1st St. Meister Rd.  $ 1,050,000.00
         
Tentative Issue 13 2013 Construction      
Clinton Ave. Jul-2013 E. 42nd Street Sheffield Twp. Line  $    750,000.00
Cooper Foster Park Rd. Jul-2013 Oberlin Ave. S. Broadway Ave.  $    750,000.00
Euclid Ave. Sep-2013 Colorado Ave. Wilson St.  $    415,000.00
Pearl Ave. Jul-2013 N. Ridge Rd. E. 36th St.  $    775,000.00
Sherwood Dr. Aug-2013 Meister Rd. W. 21st. St.  $    300,000.00
Tower Blvd. (Overlay) Aug-2013 Oberlin Ave. Falbo ave.  $    300,000.00
Washington Ave. Jul-2013 N. Ridge Rd. W. 37th St.  $ 2,000,000.00
Falbo Aug-2013 Tower 30th  $    510,000.00
34th Aug-2013 Falbo Amherst  $    120,000.00
         $ 5,920,000.00
Tentative Storm Water Fund and Issue 13 2013 Construction    
Homewood Dr. Jul-2013 Grove Ave. Tacoma Ave.  $ 1,000,000.00
         
      Total Estimated Work  $18,532,400.00